Portsmouth Ave Paving Update

Good Morning all,

The paving sub-contractor ran into some delays on their current project, so paving on Portsmouth Avenue has been delayed.
It will begin on Tuesday, September 23, 2014 and continue for approximately 2 weeks.

As always, thank you for your patience.
Jen
Jennifer Mates, P.E.
Assistant Town Engineer
Public Works Department
13 Newfields Road
Exeter, NH 03833
(603) 418-6431
jmates@exeternh.gov

Leave a comment

Filed under Around Town

Portsmouth Ave Heads Up

Good Morning all,
This is hopefully the final reminder that paving on Portsmouth Avenue will begin on Wednesday, September 17th. It is expected to take 2-3 weeks, during which time the one-way detour will be in place. This is the same detour that was used during construction.  Here is a link to the detour map: http://exeternh.gov/sites/default/files/fileattachments/portsmouth_ave_detour.pdf  Feel free to share with employees and customers.
Paving and painting are the final major tasks for this project. Thanks to all for your patience and cooperation throughout the project.
Feel free to call or email with any questions.
Thanks,
Jen

Leave a comment